Confined Space
Risks associated with confined spaces are identified, assessed and controlled in accordance with the following Action Steps and the Project Risk Assessment.
Project Risk Assessment
The Project Risk Assessment shall be used to ensure project confined space activities are identified, assessed and controlled through safe systems of work in accordance with Hierarchy of Control and the following requirements. For the purposes of this procedure a confined space means an enclosed or partially enclosed space that:
- is not designed or intended primarily to be occupied by a person; and
- is, or is designed or intended to be, at normal atmospheric pressure while any person is in the space; and
- is, or is likely to be, a risk to health and safety from:
- an atmosphere that does not have a safe oxygen level, or
- contaminants, including airborne gases, vapours and dusts, that may cause injury from fire or explosion, or
- harmful concentrations of any airborne contaminants, or
- engulfment.
Safe Systems of Work
Persons conducting confined space activities shall develop SWMS for the works being undertaken prior to obtaining a Hindmarsh Confined Space Permit for working in a confined space. The permit shall be returned to Hindmarsh on conclusion of the activities and filed. Where confined space activities result in a notifiable incident, the permit and associated records shall be retained for at least 2 years.
Hindmarsh shall not direct a worker to enter a confined space to carry out work unless the person has been issued a confined space entry permit for work. Only trained qualified personnel are to perform and enter a confined space.
The permit shall:
- Specify the confined space to which the permit relates;
- Record the names of persons permitted to enter the confined space and the period of time that the work will be carried out;
- Set out risk control measures based on the risk assessment identified in the Confined Space Permit;
- Contain space for an acknowledgement that work in the confined space has been completed and all persons have left the space.
Consideration should be given to whether the proposed work or work process will introduce any new hazards or contribute to the risks of working in the confined space. Consider any risks associated with the use of personal protective equipment (PPE) in a confined space. Using PPE may introduce new risks for those working in the space, for example the weight or discomfort of protective clothing and hearing protection.
Permit and Training
Persons conducting confined space activities, including persons entering the confined space and standby persons, shall hold Nationally Recognised Training in Confined Space addressing the:
- nature of all hazards associated with a confined space;
- need for, and appropriate use of, risk control measures;
- selection, use, fit, testing, storage of any personal protective equipment;
- contents of any relevant confined space entry permit; and
- Emergency procedures.
Air Monitoring
The Contractor conducting confined space activities shall be responsible for conducting air quality monitoring prior to entering a confined space and thereafter at defined intervals and recording results on the Confined Space Permit.
Gas detection equipment shall be inspected, maintained and calibrated in accordance with manufacturers requirements for proper operation and accuracy. Equipment shall be registered on an equipment calibration register to manage equipment specific calibration activities. The Hindmarsh Equipment Calibration Register can be used in the absence of any other register.
Work conducted in confined spaces shall not be conducted where the concentration of any flammable gas, vapour or mist in the atmosphere of the space is less than 5% of its lower explosive limit (LEL) as defined in the Confined Space Permit. The Contractor shall implement controls to warn when these limits are being reach and when these levels are exceeded, work shall cease until levels have been reduced to less than 5% of the LEL.
Emergency Management
Emergency procedures for planned works shall address the requirements of Confined Space Standing Orders identified in the Hindmarsh Emergency Management Plan. These procedures shall be documented and communicated to workers and evidenced with toolbox sign off.