Risks associated with electrical works are identified, assessed and controlled in accordance with the following Action Steps and the Project Risk Assessment.

Project Risk Assessment

The Project Risk Assessment shall be used to identify, assess and control electrical installations and equipment in accordance with the hierarchy of control to address:

Electrical Installations: construction wiring, high voltage power, switchboards and isolation.

Electrical Equipment: Testing and Tagging of extension leads, residual current devices (RCD’s) and portable electrical tools.

Electrical Workshop

Hindmarsh shall conduct the Electrical Workshop with the nominated contractor prior to commencing activities on site and to develop safe systems of work for:

  • temporary electrical installations;
  • permanent power and power on procedures;
  • evidence of electrical compliance; and
  • prevention of falling objects;

Once the initial workshop has been completed the Electrical Workshop is not required again unless the electrical supplier/installer changes.

Qualifications and Licensing

A Licensed Electrical Contractor shall be engaged to conduct work in accordance with the Project Risk Assessment and remain responsible for developing safe systems of work, including SWMS and safe work procedures for work on electrical installations.

The Licensed Electrical Contractor shall ensure workers are licensed and trained in safe systems of work involving the installation, modification, testing and certification of electrical installations.  Evidence of licensing and qualifications shall be reviewed through site induction and safe systems of work provided for the specific works.

The Licensed Electrical Contractor shall remain responsible for the training and supervision of unlicensed workers (e.g. apprentices, trade qualified workers) whilst on site.

Electrical Access and Isolation

A Services De-Energisation / Energisation Permit is required for works involving:

  • isolation, de-energisation and re-energising activities;
  • lockout and tagout of electrical isolations; and
  • working near energised parts. Work on energised equipment prohibited.

The permit shall only be issued to a Licensed Electrical Contractor when safe systems of work, including SWMS, have been developed for these specific works.

Temporary Electrical Systems Installation

The Licensed Electrical Contractor shall provide Hindmarsh evidence of inspection and compliance that assures the correct installation of temporary electrical systems for the purpose of construction including construction wiring and electrical switchboards prior to use.  This shall be conducted in accordance with relevant legislation, codes of practice and Australian standards.

The Technical Guidance Note – Temporary Electrical Installations provides guidance to site teams as to contractor requirements and deliverable for establishing and maintaining safe site electrical services as part of the construction process. 

Construction wiring shall be adequately secured, protected and clearly marked accordingly with “Construction Wiring” sticker and not be tied, bundled or grouped with permanent wiring.

Hindmarsh shall receive a copy of the Certificate of electrical safety form (ACT)  / CCEW (NSW) / Certificate of Testing and Compliance/Safety (Qld) / eCoC’s (SA) for all temporary installations once energised.

Residual Current Devices (RCD’s)

RCD protection is required for portable generators, construction wiring and electrical systems to protect workers from electrical contact. 

RCD’s shall be tested by a Licensed Electrical Contractor at maximum 3 monthly intervals and results recorded.

Technical Guidance Note – Temporary Electrical Installations provides guidance on RCD testing and required documentation. 

Tag and Test

Testing and tagging of electrical equipment shall be completed at maximum 3 month intervals by a Licensed Electrical Contractor for Subcontractor and Hindmarsh electrical equipment.  This shall be conducted in accordance with relevant legislation, codes of practice and Australian standards. Records of testing and inspection activity, including Electrical registers and Compliance Certificates, shall be provided to Hindmarsh to maintain on site.  Hindmarsh Electrical Inspection Register may be used in the absence of similar register supplied by a Licensed Electrical Contractor.

If the Licensed Electrical Subcontractor wishes to use their company template Test and Tag Register it MUST AT A MINIMUM contain the following information: 

  • Licensed Electrician name that conducted testing
  • Their license number & expiry date
  • Equipment description
  • Serial Number / Unique identifier of equipment
  • Test date
  • Next inspection test date
  • Results of trip test for Earth Leakage Devices (must contain time, PASS / FAIL is not acceptable)
  • Record of any repairs (if applicable)

If the subcontractor template does not contain the above minimum requirements or the subcontractor will not change their template to contain this, the HCA template shall be used by the subcontractor for HCA Test and Tag inclusive of temporary boards.

Monitoring of testing and tagging activities shall be conducted via Weekly SQE Inspections.

All temporary electrical installations (temporary wiring, amenities, site feeds etc) shall be re-inspected at a maximum of 6 monthly intervals and verification of certificate provided. Evidence of this inspection shall be provided by the Licensed Electrician for the site.

Technical Guidance Note – Temporary Electrical Installations provides guidance on Tag and Testing Requirements and documentation.

Core Cut and Chase Permit

A Core Cut and Chase Permit shall be completed prior to concrete cutting, coring or masonry chasing works commencing. Specific electrical controls including scanning works area for services and ensuring isolation of all services shall be triggered by completing this permit.

Energisation of Electrical Services

Prior to energising electrical services an Electrical Power On Workshop shall be completed with the nominated sub contractor to develop safe systems of work for:

  • testing and checking of main switchboard, distribution boards, circuits, solar panels and battery storage
  • Removal of temporary electrical feeds
  • Coordination of other trades that require power
  • Coordination and agreement of process required for other trades working in and around energised equipment and cables
  • Evidence of Electrical compliance

All energisation activities shall require a Services Isolation / Energisation Permit.

Once switch rooms are energised and services located on cable trays feeding these rooms are energised all works near these areas are to be conducted under the Restricted Entry Permit

The Technical Guidance Note – Electrical Switch Room Commissioning shall be tabled at the Power On Workshop to provide technical guidance for electrical switch room commissioning.

Emergency Management

Subcontractors shall be responsible for developing site specific emergency procedures for the works being conducted.  These procedures shall meet the minimum requirements of the Electrical Standing Orders in the Hindmarsh Emergency Management Plan to identify isolation processes and isolation points as well as any specific rescue training requirements.

Procedures shall be documented and communicated to workers and evidenced with sign off.