Mobile Plant
Risks associated with mobile plant are identified, assessed and controlled in accordance with the with following Action Steps and the Project Risk Assessment.
Key Points

Mobile Plant Flowchart

The Flowchart – Mobile Plant is available as a guide to managing mobile plant on site and developing safe systems of work in accordance with the below requirements.
Project Risk Assessment
The Project Risk Assessment shall be used to identify, assess and control Mobile Plant activities in accordance with the Hierarchy of Control including procedures for emergency situations.
Plant Risk Assessment
A plant risk assessment shall be completed by either a Designer, Manufacturer, Supplier, Owner or Competent Person for all plant prior to use on site. Where a suitable plant risk assessment has not been supplied, the Principal Contractor Plant Risk Assessment shall be completed in consultation with the plant operator/supplier.
Modifications that have changed the plants design shall be accompanied by a professional engineer certification declaring the modifications have not affected safety or design registration. An updated Plant Risk Assessment acknowledging these modifications shall be provided.
The plant risk assessment reviewer shall ensure hazards for each item of plant are identified and managed in accordance with the hierarchy of control. Warning devices, ROPs/FOPs, guarding, edge protection are considered the preferred higher order controls. Operator controls are considered lower order controls and on their own are not acceptable as a plant risk assessment.
Mobile Plant – General
Safe systems of work shall be developed for mobile plant by completing the Online Plant Register Inspection / Mobile Plant Pre-use Checklist and gathering related information prior to commencing on site. This shall take into consideration Original Equipment Manufacturers (OEM) manuals, output from plant risk assessments, site specific requirements and the need for ROP’S and FOPs. Once this has been completed mobile plant shall be entered onto the Plant Register.
Mobile Crane / Boom Pump
Safe system of work for Mobile Cranes and Boom Pumps shall be developed by completing a Mobile Crane / Boom Pump Set-up and gathering related information prior to commencing on site. This shall address ground location, lifting plans and lifting of materials and workers. Each proposed setup location shall be individually assessed taking into account the size and type of plant proposed with a separate Mobile Crane/Boom Pump Set-up completed for each location.
Plant that exceeds the weight/size of those nominated on the set-up shall require a new set-up assessment. If site conditions change (e.g. excavation in zone, scaffold erected in zone etc) a new set-up assessment is required.
Prior to plant being used on site ensure that an Online Plant Register Inspection / Mobile Plant Pre-use Checklist has been completed. Once this has been completed the plant shall be entered onto the Plant Register.
Tower Cranes
The Tower Crane Workshop shall be completed as follows:
Section 1 – Workshop completed 2-4 weeks from crane arrival by site team.
Section 2 – Pre Installation completed within 1 week of crane arrival by crane supplier in consultation with Hindmarsh.
Section 3 – Commissioning completed prior to crane commencing site operations.
Once this has been completed mobile plant shall be entered onto the Plant Register.
The Tower Crane Workshop (section 1) to be completed 2-4 weeks from crane dismantle by site team. All other sections of Tower Crane Workshop not applicable to Tower Crane Dismantling.
Tower / Satellite Concrete Booms
The Tower Boom Pump Workshop shall be completed 2-4 weeks from assembly on site by site team.
Critical Lifts
Hindmarsh determines that lifts that include one or more of the following criteria are deemed to be a critical lift:
TYPE 1 Critical Lift: non capacity related critical lifts (i.e. lifts must not equal or exceed 90% capacity for the crane or use multiple cranes to lift).:
- Lifting occupied work box or man box (not including first aid rescue boxes);
- Working near live overhead electricity lines;
- Has been specifically identified as critical by Hindmarsh Management or Crane Operator (e.g. fragile load, long load that exceeds limits, load with large surface area that may act as a sail, irreplaceable load;
- Erecting/Dismantling tower cranes;
- Using cranes for demolition work;
Note: If any of the above lifts exceed 90% of the cranes rated capacity or involve multiple cranes to lift (not including precast concrete panel spin-ups / rotation), they are deemed to be a TYPE 2 Critical Lift.
TYPE 2 Critical Lift: capacity related critical lifts
- Involves large loads equalling or exceeding 90% of the cranes rated capacity (not required when testing commissioning);
- Involves the use of multiple cranes to lift load (not including precast concrete panel spin-ups / rotation).
Where any of the above criteria is associated with any lift, the project team shall exhaust all possible alternatives in the first instance to eliminate the need to apply for a permit. In the event the identified critical lift criteria cannot be eliminated a Critical Lift Permit shall be completed by the project team. If the critical lift is a TYPE 2 Critical Lift the critical lift permit shall be approved by State SQE Manager prior to the lift occurring. The Critical Lift Permit shall be issued in addition to the completion of Mobile Crane/Boom Pump Set-up if a Mobile Crane is to be used to complete the Critical Lift.
Above Ground and Underground Services
The Project Risk Assessment shall be used to develop safe systems of work and managing potential hazards related to above ground and underground services by:
- identifying and locating services;
- managing works adjacent to services; and
- liaising with asset owners.
In addition to the above controls, underground services shall be managed in accordance with the Excavation Permit and the requirements of the Excavation Procedure.
Operator Competency
The Online Plant Register Inspection / Mobile Plant Pre Use Checklist and Tower Crane Workshop (section 3) shall be used to record the type of operator licencing, qualifications or competency requirements to operate the mobile plant on site. These requirements shall be verified at Site Specific Inductions and attached to their Hammertech induction profile. Competency requirements are documented in the Technical Guidance Note – Verification of Mobile Plant Operator Competency to assist this process.
On Site Movement Plan
The Project Risk Assessment shall be used to document potential hazards and controls regarding plant and vehicle movements on site. Safety documentation (e.g. SWMS, On Site Movement Plan, Toolbox and Pre Start Meetings) shall be used to communicate activities. These shall take into consideration site characteristics, exclusion zones, warning devices and plant/vehicle/worker interactions.
Technical Guidance Note – Spotters
Technical Guidance Note – Access and Egress
Technical Guidance Note – Exclusion Zones
Plant Inspection, Maintenance and Monitoring
The Online Plant Register Inspection / Mobile Plant Pre-Use Checklist and Tower Crane Workshop (section 3 – Commissioning) shall be used to identify plant inspections and maintenance specific to the needs of each type of plant. Inspections shall be in accordance with regulatory inspections, registrations and manufacturers requirements, including pre-start inspections and/or commissioning prior to commencing on site.
The Plant Register shall be used to manage ongoing maintenance requirements including nominating scheduled maintenance frequencies and specific dates for the next maintenance to be performed;
This register shall identify rigging and lifting equipment (e.g. chains, slings, lifting beams, shackles etc) with current inspection, testing and certification status of each item identified unless a register of such equipment is supplied by others.
Hindmarsh shall be responsible for verifying that inspection and maintenance is conducted while the plant is on site. The Plant Register shall be reviewed weekly to verify records of inspection and maintenance activities have been completed. Corrective actions shall be initiated through OnSite > SQE > CAR’s when planned activities have not been completed.
In addition to the above, the use of plant, including inspection and maintenance activities, shall be monitored through Weekly SQE Inspections, SWMS Engagement or project specific Safety Meetings.