Structural Steel
Structural Steel Flowchart

Project Risk Assessment
Project specific Structural Steel activities shall be identified, assessed and controlled in accordance with the Project Risk Assessment. The Project Risk Assessment shall be used to assist in the development of safe systems of work including procedures for emergency situations.
Design Management
A Design Plan for Structural Steel activities shall be developed and certified by a Structural Engineer qualified as a member of the Institution of Engineers Australia to address the approval of any proposed proprietary or manufactured:
- inserts,
- fixings,
- anchorage; and
- bracing
Shop Drawings and Marking Plans shall be provided by structural steel supplier as detailed in the Structural Steel Workshop.
Safe Systems of Work
A Structural Steel Workshop be conducted with the relevant Structural Steel contractor in consultation with the relevant Crane Crew prior to activities commencing on site. The workshop shall be used to develop safe systems of work, including SWMS, to address:
- that a Lift Plan has been developed in consultation with crane crew. Note: If operating above 90% of the cranes capacity a Critical Lift Permit MUST be completed;
- erection, bracing and stripping;
- protection of workers under and around Structural Steel;
- falls and falling objects;
- unloading and slinging elements and cranage requirements; and
- the protection of elements and bracing from damage by inadvertent contact with Mobile Plant or other site activities.
Inspection Requirements
Installation – The Contractor shall provide ITPs and an engineer’s sign off to Hindmarsh for verification that Structural Steel elements have been installed in accordance with the requirements of the Design Plan.
Ongoing Inspection – Ongoing inspection of braces / props / fixtures / bolts shall be completed by contractor in accordance with the frequencies and requirements of the Design Plan. Hindmarsh shall conduct daily visual inspections of braced and bracing structural steel elements and communicate any corrective actions through OnSite > SQE > CAR’s.
Where engineers advice has been received that braced and bracing structural steel elements are no longer active, ongoing inspections are no longer required.
In addition to the above, Structural Steel activities shall be monitored through the Weekly SQE Inspections and SWMS Engagement activities.