Risks associated with Tilt-up/ Precast Concrete activities are identified, assessed and controlled in accordance with the following Action Steps and the Project Risk Assessment.

Project Risk Assessment

Project specific Tilt-up / Precast activities shall be identified, assessed and controlled in accordance with the Project Risk Assessment. The Project Risk Assessment shall be used to assist in the development of safe systems of work including procedures for emergency situations.

Design Management

A Design Plan for Tilt-up/Precast activities shall be developed and certified by a Structural Engineer qualified as a member of the Institution of Engineers Australia to address:

  • design and construction of panels including identifiers for each panel;
  • lifting points and panel placement;
  • erection requirements that include panel bracing and details of anchorage designs;
  • inspection requirements for panels, lifting points, bracing prior to, during and after installation.

Tilt-up / Precast Design

The structural design drawings, including the approval of any proposed proprietary or manufactured inserts and fixings, shall be certified by a Structural Engineer.  Further requirements are detailed within the Tilt-up / Precast Workshop.

Tilt-up / Precast Shop Drawings must be available on site at time of installation of panels.  Inclusions within the shop drawings are discussed and recorded during the Tilt-up / Precast Workshop.

Safe Systems of Work

A Tilt-up / Precast Workshop shall be conducted with the relevant Tilt-up/Precast contractor in consultation with the relevant Crane Crew prior to activities commencing on site.  The workshop shall be used to develop safe systems of work, including SWMS, to address:

  • that a Lift Plan has been developed in consultation with crane crew.  Note: If operating above 90% of the cranes capacity a Critical Lift Permit MUST be completed;
  • erection, bracing and stripping;
  • protection of workers under and around Tilt-up/Precast;
  • falls and falling objects;
  • unloading and slinging panels and cranage requirements and
  • the protection of panels and bracing from damage by inadvertent contact with Mobile Plant or other site activities.

Inspection Requirements

Installation – The Contractor shall use the Tilt-up/Precast Inspection Checklist to provide Hindmarsh verification that Tilt-up/Precast panels have been installed in accordance with the requirements of the Design Plan.

Ongoing Inspection – The Contractor shall use the Tilt-up/Precast Inspection Checklist to provide Hindmarsh evidence of ongoing inspection of braces  / props / fixtures / bolts  conducted in accordance with the frequencies and requirements of the Design Plan.  Hindmarsh shall conduct daily visual inspections of braced and bracing concrete elements and communicate any corrective actions through OnSite > SQE > CAR’s.

Where engineers advice has been received that braced and bracing concrete elements are no longer active, ongoing inspections are no longer required.

In addition to the above, Tilt-up/precast activities shall be monitored through the Weekly SQE Inspections and SWMS Engagement activities.