Working at Heights
Risks associated with working at heights are identified, assessed and controlled in accordance with the with following Action Steps and the Project Risk Assessment.
Project Risk Assessment
The primary methods to prevent falls from height and falling objects shall be managed through Demolition, Excavation, Formwork, Scaffold and Tilt Up/Pre Cast procedures.
Proposed working at heights activities not covered by these procedures shall be identified, assessed and controlled in accordance with the hierarchy of control in the Project Risk Assessment and the following requirements.
Fall Restraint/ Fall Arrest Equipment
Training – Persons using fall restraint/fall arrest equipment shall hold Nationally recognised Work at Height training course or applicable high risk construction work license including EWP >11m, Riggers/Scaffolders tickets.
Maintenance – Evidence of equipment maintenance and inspections shall be provided prior to works commencing and continue throughout the project in accordance with an equipment maintenance schedule.
Harnesses shall be inspected by an Independent Inspector at a frequency of no more than 6 months.
Harnesses shall also be inspected daily prior to task commencing.
The Hindmarsh Harness Permit – Inspection shall be used if inspection records are not otherwise supplied by the Subcontractor.
Attachment Point Design – Engineering design for proprietary attachment points (e.g. eye bolts, static lines) shall be in accordance with manufacturers requirements and provided and certified by a qualified Engineer with experience in fall restraint/fall arrest equipment and a member of Engineers Australia. Evidence of qualifications and competency must be kept on site.
Where fall restraint/fall arrest equipment is attached to a structural element (e.g. a concrete column) this shall be done so by a person holding Riggers (All) / Scaffolders (Advanced / Intermediate) high risk work license.
Harness Permit
The Harness Permit shall be issued by Hindmarsh when safe systems of work, including SWMS and associated design, installation, maintenance, inspection and training records are developed where the risk of working at heights is identified.
The Harness Permit shall be approved by the SQE Manager when safe systems of work have been developed and evidence of SWMS, equipment inspections, design and installation information of attachment points and training records have been received.
A Harness Permit is not required when using a harness as a secondary control measure such as EWP, Confined Space and Man Box.
Temporary Edge Protection
Temporary edge protection systems (including proprietary and engineered systems) shall:
- be designed by a Structural Engineer with experience in structural support systems;
- have changes to the design or installed system approved by the Structural Engineer;
- be installed and inspected by a Ticketed Scaffolder, or a Rigger, or a worker trained in the use of the system, prior to handover. Evidence of the initial inspection shall be documented and provided to Hindmarsh.
Ongoing inspections of installed systems shall be conducted monthly by a Ticketed Scaffolder, or a Rigger, or a worker trained in the use of the system, documented and provided to Hindmarsh.
Ladder Use
Ladders shall primarily be used as a means of access (e.g. access to mobile scaffolds, formwork decks etc) and not a working platform. The use of ladders (i.e. A frames/rung ladders) for other purposes shall only be considered if it can be demonstrated that safer alternatives, such as scaffolding or elevating work platforms, Platform Ladders or trestles are not reasonably practicable.
Where Scaffolding, Elevating Work Platforms, Platform Ladders or trestles are not reasonably practicable, safe systems of works shall be developed to address potential hazards and controls relating to working from a ladder. These may include a SWMS, Risk Assessment or other standard operating procedure. In these cases the safe use of ladders shall only be used for light duty work of short duration.
Ladders must meet the requirements of AS/NZS 1892.5 2000. Domestic ladders are prohibited from use at Hindmarsh.
Access and Egress
The primary methods to manage the safe access and egress for areas where work at heights shall be managed through Demolition, Excavation, Formwork and Scaffold procedures.
Where access and egress is not covered by these procedures potential access and egress hazards shall be identified, assessed and controlled in accordance with the hierarchy of control in the Project Risk Assessment.
Core Cut and Chase Permit
A Core Cut and Chase Permit shall be completed prior to concrete cutting, coring or masonry chasing works commencing. Specific falls / falling objects controls including work platforms, exclusion zones, spotters and penetration covers shall be triggered by completing this permit.
Emergency Procedures
Emergency procedures shall be established specific to the scope of works, including actions to be taken after an arrested fall has occurred. These procedures shall be identified through SWMS, the Emergency Management Plan Standing Orders and Harness Permit -Emergency Guidelines.
Roofing Management
Where identified in the Project Risk Assessment, a Roofing Management Workshop shall be held with the relevant subcontractor.